Installation of dewatering, disinfection and drying of sludge "ДЕКО-СИО"
ТУ 4859-021-10442696-2007
Ecological certificate
Certificate of conformance
Explication
1 – receiver tanks | 6 – sludge unloading assembly |
2 – filtration sleeves | 7 – stop valves |
3 – water receiving trays | 8 – sludge dispensing system |
4 – stop valves | 9 – air heating and distribution system |
5 – stop valves | 10 – control valve |
Installation "ДЕКО-СИО" is operates as follows:
Sludge feeds to a receiver tanks 1 and then unload by stuff from receiver tanks into filtration sleeves 2, where the sludge will remain 5(7) days. Feeding of sludge from receiver tanks 1 into filtration sleeves 2 is realized through the stop valves 4.
As a result of long-term heat treatment of sludge (at a temperature 80 – 85оС) it is provided a destruction of pathogenic microflora and helminth eggs. At the same time, due to high moisture- resistance and vapor permeabilty of the material of filtration sleeves, during stay in a sleeve the humidity of sludge decreased up to 5-10%. Air supply into filtration sleeves 2 is realized through stop valves 5.
Dried up and sterilized sludge is unloaded manually from filtration sleeves into a plastic flask, and after that is poured into a polyethylene bag (package) and tightly soldered. The bag is located on a temporary storing position.
The unloading of sterilized sludge from the filtration sleeves 2 is realized through a binded mouth 6.
The mounted installation of dewatering, disinfecting and drying of sludge
"ДЕКО-СИО -3,2М/2".
Designation when order (example):
Installation of dewatering, disinfecting and drying of sludge ДЕКО-СИО-3,2М/2. ТУ 4859-021-10442696-2007.
Installation "ДЕКО-СИО-3,2М/2" is intended for dewatering, disinfecting and drying of sludge.
Engineering performance of the installation
№ | Engineering performance | Point of measure | "ДЕКО-СИО-3,2М/2" |
1. | Dimension (not more), L ´ B ´ H | m | 3,938 х 2,870 х 4,900 |
2. | Installed capacity | kW | 8 |
3. | Power consumption | kW | 4 |
Manufacturing data of the installation
№ | Indicators name | Point of measure | at the input | at the outlet |
1. | Relative humidity | % | 95-99 | 5-10 |
2. | Presence of helminth eggs | - | available | available |
3. | Presence of pathogenic microflora | - | available | available |